Acceptance Criteria: Review the SAT document for tolerances (speed, dimensions, load, cycle times). ±5% deviation may be allowed; check specifics.
Remedies Clause: Identify remedies:
Price reduction / partial refund
Replacement unit
On-site correction by supplier
Ensure timelines are defined
Local Repairs: Supplier-approved local repair may be reimbursed—always get written consent first.

Good documentation strengthens your claim:
Measure machine dimensions accurately (length, width, height, forks, wheelbase)
Record video showing AGV operation highlighting the discrepancy
Collect load test or cycle time data if below spec
Compare results against SAT requirements
Prepare a Non-Conformance Report (NCR) with photos, measurements, and video timestamps
Tip: Send the NCR within 48 hours of SAT to preserve claim rights.
| Issue | Typical Action |
|---|---|
| Minor (≤5% deviation) | Price reduction or software tweak |
| Medium (5–10% deviation) | Replacement part or onsite fix |
| Major (>10% deviation) | Full replacement or contract termination |
Key: Always negotiate in writing with attached measurement evidence.
Check Incoterms: DDP / CIF → supplier may handle; FOB → you may organize return
Get customs export permit
Use experienced freight forwarder
Document machine condition with photos and packing checklist
⚠️ Returning the AGV is costly; local fixes are often faster if supplier approves.
Obtain written approval from supplier before any repair
Use qualified US machine shop or integrator
Document repair with invoices and photos
Submit for reimbursement per contract
Without approval, supplier may reject claim
Check governing law & dispute resolution: often Hong Kong, Singapore, China
Arbitration: CIETAC, ICC, or US courts if specified
Keep all communications, photos, reports, emails
Avoid informal verbal claims—they carry little weight
SAT identifies discrepancy → document with photos/videos
Draft NCR → send to supplier immediately
Review contract remedies → propose resolution (price reduction, onsite fix, local repair)
Seek written approval for any local fix or replacement
Track repair costs, communications, and approvals
Escalate to arbitration if no resolution within contract timeline
Document everything immediately during SAT
Know your contract: acceptance criteria, remedies, and local repair clauses
Never modify the machine locally without supplier approval
Legal recourse is possible but slower and costly—negotiate first
FREE ENGINEERING SUPPORT Stop Gambling on Generic Platforms. Get an AGV/AMR Tailored to Your Warehouse.Buying automated guided vehicles involves complex safety standards (CE/ANSI), navigation setups (Laser SLAM), and ERP system integration. Don't risk your factory safety with middle-men. ✓ 100% Direct Factory: Customized payload up to 5 Tons. ✓ Free CAD Simulation: Send us your layout, and our engineers will simulate the optimal AGV routes. ✓ Global Support: Overseas installation guidance & local maintenance partners. |